Fabulous Space – Main Floor
Things are going according to plan! Installation of the second floor joists is nearly complete. The temporary bracing for the exterior walls […]
Things are going according to plan! Installation of the second floor joists is nearly complete. The temporary bracing for the exterior walls […]
What a difference a few days and skilled framers can make on a project! Westridge Construction and Laron Builders have been hard […]
While most of us were enjoying the weekend, the masons from Archpoint Masonry Inc. in Regina were hard at work – building […]
What has more choices than a hipster, artisanal coffee house? How about an Input Housing field trip to Cupboard Brothers Cabinet Factory […]
The rain has temporarily slowed construction, but it has not dampened our spirits. Soon the walls on the main floor will be […]
The Fall 2019 edition of Western Exteriors Magazine is out!! A few months ago, we were contacted by Western Exteriors Magazine, which […]
The race is on to get the building framed and enclosed before the cold weather arrives. The framing crew, Laron Builders, is […]
Today was an exciting day at the Input Housing building site! Westridge Construction was casting the concrete slab in the crawl space. […]
The installation of the aggregate base for the concrete slab in the crawl space is well underway. The grade beam and perimeter […]
Well it looks like construction of the Input Housing condominium project hit a low point at the end of last week! To […]